|
|
SEWER AUTHORITY
UPPER PROVIDENCE TOWNSHIP
APRIL 9, 2008
The regular monthly meeting of the Upper Providence Township Sewer
Authority was held on April 9, 2008 in the Township Building. It was
called to order at 7:35 p.m. by Chairman, Robert G. Donze.
|
|
|
THOSE ATTENDING |
|
Mr. Michael Byrne
Mr. John Ciminera
Mr. David Decker
Mr. Robert G. Donze
Mrs. Patricia Hall, Office Manager
Mr. James C. Kelly, Engineer
Mr. Donald D. Phillips
Mr. Robert L. Pinto, Solicitor
Mr. Richard T. Spielman, Operations Manager
Mr. Frank Troilo
Mr. David A.Whinfrey
Others attending: Mr. Ed Cashman
|
 |
| PUBLIC COMMENT
|
|
None.
|
 |
| MINUTES |
|
The minutes of the meeting of March 12, 2008 were reviewed.
MOTION: Mr. Donald D. Phillips moved to approve the minutes of the meeting
of March 12, 2008 as presented. Seconded by Mr. David A. Whinfrey.
Motion carried unanimously. (MOTION 08-04-32)—check date
|
 |
| INCOME AND EXPENSES
|
The voucher list for April 9, 2008 was reviewed. Expenses
totaled $66,434.30.
MOTION: Mr. John Ciminera moved to approve the voucher list of April 9,
2008 as presented. Seconded by Mr. Michael Byrne. Motion carried
unanimously. (MOTION 08-04-33) |
 |
| REPORTS OF OFFICERS
- None |
|
MANAGERS REPORT
There has been no change in the number of permits issued (148) for sewer
connections on the SASSSE Project. On the WWASSE project, 180 permits and
177 grinder pumps have been issued. Three permits have yet to be
completed.
Ninety-two connection permits have been approved, and 81 low-pressure and
10 gravity connections have been completed in the Gelbert Street/Farnum
Road Sewer Extension Project. Twenty permits have yet to be completed.
The meter at Braves Trail pumping station has stopped working. LRM will
investigate.
Kelly Engineers is currently addressing the following issues: A new pump
station maintenance contract (completed on January 8, 2008); a bid
proposal for the new generator (bid has been awarded); a report to DEP
regarding I&I (completed and submitted to DEP, who wants a more detailed
plan); and the need for a bid package to cover the four-year cleaning/root
cutting maintenance program (Kelly and Close Engineers authorized to
prepare the bid package).
Mr. Russ McIntosh has submitted his draft analysis of the Aqua contract
proposal and the Authority’s possible options to Mr. Pinto for review.
Following his review and a meeting with Mr. Spielman and Mr. McIntosh, a
meeting will be scheduled with the Finance Committee, tentatively before
the May Authority meeting.
A section of 8” main at Second Avenue and Evans, which has been a trouble
spot, was televised by Aqua personnel at Mr. Spielman’s request. The first
75 feet of main had heavy root growth and the pipe joints were not in good
condition. There was also a sag in the line. Mr. Spielman is recommending
that Kelly and Close Engineers prepare a bid package to replace the first
100’ of terra cotta main with plastic from manhole 2-11 toward 2-10 to
eliminate both the root problem and the sag in the main.
MOTION: Mr. David Decker moved to authorize Kelly and Close Engineers to
prepare a bid package to replace the first 100’ of terra cotta main from
manhole 2-11 toward 2-10. Seconded by Mr. Donald D. Phillips.
Motion carried unanimously. (MOTION 08-04-34)
Mr. Spielman referred to a spreadsheet he had prepared on UPTSA’s flow
meter summary for 2007. He noted the Authority’s percentage of plant flow
was 37.49% and its percentage of plant capacity was 29.15%. He compared
this to the previous year.
Mr. Donze referred to an e-mail from Mr. M. Majeski. Mr. Kelly has
responded to this and has asked him for more information. Mr. Spielman
noted that DEP is in the process of trying to institute a couple of
regulations regarding outflow into at least one stream. If the regulations
were followed as now proposed, it would cost $15,000,000.00 to upgrade the
Southwest treatment plant to the proposed specifications. A group of sewer
authorities has come together to oppose these proposed regulations. Mr.
Majeski asked if we would be interested in becoming involved. At this
point, Mr. Spielman is not in a position to recommend anything, but is
hoping to have more information before the Engineering Committee meeting.
Mr. Donze asked about the March 31 letter to Mr. Spielman from Mr. Edwin
Hall of Wooded Way. Mr. Spielman reported that he had spoken with Mrs.
Hall regarding the letter. He noted that for a number of reasons, we would
be reviewing our policy, but he could not guarantee that it would change.
He also noted that we did not buy the pumps on Ruskin Lane; that
basically, what we install, we own, and what the customer installs, he/she
owns. Mr. Spielman will be meeting with Mr. Kelly to discuss the policy
and come up with a recommendation to present to the Engineering Committee.
REPORTS OF COMMITTEES
An Engineering Committee meeting is scheduled for 5:30
p.m. on April 23 to discuss the I&I issue.
|
 |
| REPORTS OF CONSULTANTS |
|
MR. JAMES C. KELLY, KELLY and CLOSE ENGINEERS
Present at last night’s meeting of CDCA were representatives from
Nether Providence, Newtown Township Municipal Authority and Edgmont
Township. At the last regular meeting of the supervisors, Nether
Providence Township had approved the Supplemental Agreement with a
resolution that amendments be made to clarify the intent of the document.
The CDCA board approved the proposed amendment and authorized the
solicitor to prepare the amended agreement for distribution to all
municipalities for approval and execution. The proposed modifications were
not considered to be substantive changes to the Agreement, and no
objection is anticipated from the municipalities who have previously
approved the first draft of the agreement.
CDCA approved the recommendation of their finance committee to commence
the Crum Creek Capital Improvement Program. The project schedule was
available and bids are scheduled for opening in November, 2008. Copies of
the proposal of PFM Group, financial consultants, was distributed.
Mr. Kelly is recommending that the Authority consider meeting with a PFM
representative for a presentation of financing alternatives for our
projects.
Regarding the pump station upgrade for the mobile diesel generator, this
week the contractor (Couzins, Inc.) has submitted the required performance
bond and signed and notarized the Articles of Agreements from the
contractor. As the documentation is adequate, subject to the approval of
the Solicitor, Mr. Kelly will issue the notice to proceed, upon execution
of the documents by the Authority.
Kelly and Close Engineers is preparing the bid documents for the cleaning
and root cutting contract. Mr. Kelly has met with Mr. Mark Schneider of
Tri State Grouting to discuss a new alternative to pipe grouting and slip
lining that is “Manhole Slip Lining.”
Payment request Number 9 for the Rose Tree Park Comfort Station has been
received in the amount of $62,404.04, the total value of the work
completed for this period. Mr. Kelly is recommending that the Authority
approve this payment. The amount of retainage to be held in escrow until
the contractor completes some final restoration work will be $10,000.00. A
draft of the submission to the County was attached to Mr. Kelly’s report.
MOTION: Mr. David A. Whinfrey moved to approve the release of payment
request
No. 9 in the amount of $62,404.04 to N. Abbonizio Contractors, Inc. for
the
total value of the work on the Rose Tree Park Comfort Station which has
been completed for this period. Seconded by Mr. Donald D. Phillips.
Motion carried unanimously. (MOTION 08-04-35)
With regard to Kenmore Woods, Mr. Kelly has received escrow release Number
1 in the amount of $37,260.00, the total value of the work completed for
this period. He is recommending that the Authority approve this release.
The amount of retainage to be held in escrow until the contractor
completes this project is $148,983.75.
MOTION: Mr. Michael Byrne moved to approve Kenmore Woods escrow release
No. 1 in the amount of $37,260.00 to the contractor for the total value of
the work completed for this period. Seconded by Mr. Donald D. Phillips.
Motion carried unanimously. (MOTION 08-04-36)
Mr. Donze asked Mr. Kelly for a brief summary of where we stand now in
connection with CDCA. Mr. Kelly referred to the Resolution awaiting
signature tonight, which says essentially that the UPTSA gives Upper
Providence Township permission to join another authority, CDCA. Notice of
this Resolution shall be published at least one time in the legal
periodical of Delaware County and in a newspaper published and of general
circulation in Delaware County.
MOTION: Mr. John Ciminera moved to approve Resolution No. 01-08-04-09 of
Upper Providence Township Sewer Authority consenting to the Township of
Upper Providence becoming a member of the Central Delaware County
Authority (CDCA). Seconded by Mr. David Decker. Motion carried
unanimously. (MOTION 08-04-37)
Mr. Kelly referred to the section of the Resolution which states “that the
Authority shall file an application with the Secretary of the Commonwealth
of Pennsylvania in accordance with the requirements of 53 Pa. C. S. A.
5604(d).” The Secretary of the Commonwealth has to approve the addition of
the three new members to CDCA. It is anticipated that we will be getting
the approval of the Secretary of the Commonwealth and the first payment
would be necessary in June of this year. Following that should be the
approval of the 537 Plan.
There was a discussion about sewers and financing costs and options.
MR. ROBERT L. PINTO, SOLICITOR
Mr. Pinto noted that we had borrowed $3,500,000 from DVRFA and
specifically indicated which projects that would be for. There was money
left over, so in 2003 the project scope was expanded to include Gelbert
Street and Farnum Road. There is still money left over. Mr. Pinto has
prepared a Resolution amending our prior description to include the Ridley
Creek Sewer Project.
MOTION: Mr. John Ciminera moved to accept Resolution No. 02-08-04-09
amending and expanding the project description for the $3,500,000
guaranteed sewer revenue note series of 1999 to include new sewer
projects. Seconded by Mr. Michael Byrne. Motion carried unanimously.
(MOTION 08-04-38)
A discussion followed on future projects, costs, and resident
notification.
Mr. Ciminera will coordinate a Finance Committee meeting to be held before
the May Authority meeting. When the Authority looks at financing
alternatives, Mr. Pinto reminded the board that we have had good advice
from Gordon Walker over the years.
|
 |
| MISCELLANEOUS |
|
MR. GEORGE GOLDEN’S REPORT
In response to a call of back-up pump run at the Braves Trail station on
March 2, Mr. Golden cleaned the floats, obstructed by debris and grease,
and monitored operations. Later, he cleaned the wet well.
On March 8, Mr. Golden responded to calls from dialers of power failures
and back-up pump runs at the Braves Trail, Winter Street, Valley View,
Cedar Meadow, and Megan Circle stations. He notified PECO and towed the
generator to Braves Trail. Using vacuum trucks, he de-watered the wet
wells until power was restored; and installed new control relays, which
were burned due to a power surge at the Winter Street station. The dialer
at the Winter Street station shorted on March 10 due to a power surge. A
new dialer was ordered for the station. There were no incidents at any of
the other pumping stations.
MOTION: Mr. David A. Whinfrey moved to adjourn the meeting of April 9,
2008.
Seconded by Mr. Michael Byrne. Motion carried unanimously.
(MOTION 08-04-39)
|
 |
The meeting ended at 8:56
p.m.
Mrs. Stella B. Thompson
Approved ______________________ |
|
| |